As of |
Slippage |
|
|
|
31 January 2008 |
(+/-) |
Target |
Actual |
|
sales & mktg |
0.00 |
13.91 |
13.91 |
| staking & design |
0.00 |
10.68 |
10.68 |
| delivery |
-5.37 |
14.36 |
8.99 |
| installation |
-10.24 |
10.24 |
0.00 |
|
-15.61 |
49.20 |
33.58 |
|
|
Note: Revised schedule was based on the updated plans and schedule attached to first progress billing on 19 June 2007 |
|||
Payment (including advance payment of 19.5%) as of January 31, 2008:
|
Activities |
Total Contract, Euro |
Payment, Euro |
% Contract |
Pending, Euro |
|
Onshore (labor) |
3,498,000.00 |
1,084,352.37 |
31.00% |
|
|
Offshore (materials) |
14,000,000.00 |
4,976,115.70 |
35.54% |
4,906,686.68 |
· Materials Delivery Ongoing: France via Cebu then Masbate by boat
· Survey and Design: completed as of 31 January 2008
· Target in 2008: Electrification of at least 113 barangays March-May 2008 using PV-SHS