Project Status

 

Title:    Philippine Rural Electrification Service Project

Implementing Agency:    National Power Corporation - Small Power Utilities Group

Financing:    French Protocol

                        Natexis                        Euro10,498,800.00

                        BNP Paribas                 Euro 6,999,200.00

Loan: 15 years + 10 years grace period., interest rate 0.4% per year; payment semiannual, Euro currency

Contracting Period: 877 Calendar days

Notice to Proceed: 18 January 2007

Contract End: 13 June 2009

Contractor: ETDE of France and Paris-Manila Technology (PAMATEC)

Work Scope: Engineering, Procurement, Sales and Construction

Target Area Coverage: Masbate & Ticao

                        Number of Barangays:            128

                       Number of Households:           18,0000

 Design Result:

Type

Proposed

Actual

 

Barangay

Household

Barangay

Household

Mini-Grid (MG) System

 

 

13

1,644

PV Solar Home System

 

 

26

1,017

PV / MG

128

18,000

87

13,224

TOTAL

128

18,000

126

15,885

 

 STATUS as of:

 

Project Director:                        Lorenzo S. Marcelo, VP-NPC SPUG

                                                  Tel No. 09285026467

                                                   lsmarcelo@napocor.gov.ph

 

Project Management:               Rene B. Barruela

                                                   Tel No. 09189085285

                                                   rbbarruela@napocor.gov.ph

 

Consortium Management:

Consortium Project Manager:     Pavil Ranik

PAMATEC Project Manger:           Philippe Saubier

                                                     Tel No. 09188308868

                                                     psaubier@pamatec.com.ph